Variant manufacturing and S/4 Hana

Can the new S/4 Business Suite deliver on the promise of a "digital core for digital business processes" for supply chain and logistics as well? An initial reality check reveals: The goal is becoming (more) visible on the horizon with each new release. But there is still a long way to go until then.
Elmar Thomson, BTC
April 3, 2016
2016
avatar
This text has been automatically translated from German to English.

The idea behind Industry 4.0 is quickly put on paper: In a nutshell, from a technical perspective, it is the value-creating combination of automation and information technology in production.

All elements involved in a process - machines, products, systems, people, etc. - communicate and organize themselves in real time. From a business management/organizational perspective, manufacturing companies are enabled to develop the appropriate response to the increasing intensity of competition and atomization of demand in this way.

The buzzword that is often used in this context is batch size 1, by which is meant that in the course of the digital transformation even series manufacturers can transform into variant manufacturers. In some cases, they may even become one-off manufacturers.

Such a change undoubtedly has far-reaching effects on the design of corporate and production processes and poses new challenges in terms of information flow and integration.

At this point, SAP wants to simplify the transition to the digital world for companies with S/4. The heart of S/4 Enterprise Management is the so-called "digital core for digital business processes".

This raises the question of whether the suite with its new range of functions can contribute significantly to the Industry 4.0 idea. After all, the efficient control of variant-rich production is often not one of the great strengths of traditional ERP systems.

Often, the efficiency of ERP applications is increased by specialized add-ons, such as BTC VariantDirekt, to fully cover the specific requirements in industries such as furniture or mechanical engineering.

In this way, capacity planning can be realized that allows very short-term delivery commitments based on real-time information. Complex sequence planning can be validated via upstream simulations without these processes resulting in losses in runtime.

It is also possible to integrate special designs into production at short notice without causing equally long planning and setup times. The add-on supports all relevant process steps for variant-rich make-to-order manufacturers - from the creation of bills of materials and scheduling to the provision of design drawings.

New options through Hana

The introduction of the high-performance SAP Hana platform opens up new options for reacting more quickly and, above all, more easily to changing requirements. From a technical perspective, SAP Hana has everything it takes to process large volumes of data in real time.

This provides the opportunity to dispense with classic MRP lists and to carry out material requirements planning on the fly. Even the future significance of special planning solutions such as SAP APO (Advanced Planning and Optimization) can be questioned with this approach.

The prospect sounds tempting. A first look reveals that further functional areas have been Hana-optimized in the 1511 release of S/4. The suite provides all functions relevant to logistics - from sales and distribution to inventory management, material requirements and capacity planning, and purchasing.

In addition, the version includes a significantly leaner data model for materials management and the first approaches to Hana-optimized planning.

The original project name Simple Logistics, under which the realization of the functions for supply chain management and production planning was advanced, already carried the objective of simplification in its name.

Similar to Simple Finance (now S/4 Finance), the number of tables in Inventory Management, some of which were introduced for pre-compressed intermediate aggregates, has been significantly reduced. Now, only four tables are used - one each for storage location data, material master data, inventory management and the material document.

In short, thanks to the power of the SAP Hana in-memory platform, master and transaction information can now be managed cleanly separately, and the historically grown, less transparent table nestings become obsolete.

In the new system, information is no longer stored redundantly, which is inevitably advantageous for performance and storage requirements. At the same time, transparency and data security increase, since the risk of transfer and incorrect posting between aggregates does not exist in the new system.

Compared to the traditional ERP system, including the products once introduced as New Dimension, the inherent planning architecture in S/4 is visibly simplified. This applies in particular to the integration with the SAP APO planning component, whose functions will probably be successively transferred to the Digital Core.

The MaxDB-based liveCache, an early form of in-memory processing, now merges with S/4's Hana platform, resulting in a simplification of the architecture. With MRP live, a very high-performance planning engine is now available in the ERP core.

MRP runs can thus be executed in significantly shorter cycles, and multi-level individual customer planning becomes obsolete. Which planning heuristics are ultimately executed in the ERP or Hana-based is stored in the material master and is queried on the fly by the MRP Live Dispatcher.

In addition to classic planning calculations, MRP Live also supports dedicated planning for selected materials at a selected location and the associated supplying production plant.

The calculation can cover the entire supply chain - i.e. including the components in the production plants. Planning based on scheduling is also supported.

S/4 also includes the APO production and detailed planning component PP-DS as a co-installation. This allows planned orders to be created synchronously without interrupting the MRP process in ERP.

Redundant master data storage and time-consuming data transfer between systems are consequently a thing of the past. An important element of digitization is the user-friendliness of software applications. With the so-called "Fioris", SAP now offers an app-based operating concept that significantly contributes to simplified work.

For example, the smart business application "MRP Cockpit" visualizes material shortage situations in the planning process at a glance. System-based simulation supports the planner with already evaluated solution options. SAP has also released a series of transactional and analytical apps for logistics with the 1511 release.

Releases 1602 and 1605

The development is running at full speed and more apps can be expected with the upcoming releases 1602 and 1605. Until then, it might be necessary to switch between user interfaces.

For example, in the order-to-cash process flow, the creation of a production order is now also carried out via a Fiori app, while the goods receipt posting of ordered parts is still processed in the traditional WebGUI.

To be fair to SAP at this point, the current shortcomings are simply due to the size of the task. We can also expect close integration of advanced warehouse management and control (EWM) and transportation management (TM) with the Digital Core. Likewise, Hana-optimized variant configuration and sequencing of bottlenecks are on the developers' to-do list.

Conclusion

Even if not everything is complete from a process perspective: The direction SAP is taking with S/4 Hana Enterprise Management promises to be the appropriate platform for implementing Industry 4.0 concepts.

It is already apparent what new possibilities S/4 offers in production planning and control, while the Hana platform brings impressive capabilities for integrating and processing multiple sources of data and information.

This also includes broad support for different operating models and interoperability with cloud applications. S/4 gives a clear indication of what not only interested manufacturing companies can expect (and demand) from a modern ERP suite in the future.

With the upcoming releases, we can expect a number of optimized applications that will make it harder not to look more closely at S/4 in your own digitization strategy.

avatar
Elmar Thomson, BTC

Elmar Thomson is Senior Business Development Manager in the Industry and Services division at BTC Business Technology Consulting.


Write a comment

Working on the SAP basis is crucial for successful S/4 conversion. 

This gives the Competence Center strategic importance for existing SAP customers. Regardless of the S/4 Hana operating model, topics such as Automation, Monitoring, Security, Application Lifecycle Management and Data Management the basis for S/4 operations.

For the second time, E3 magazine is organizing a summit for the SAP community in Salzburg to provide comprehensive information on all aspects of S/4 Hana groundwork.

Venue

More information will follow shortly.

Event date

Wednesday, May 21, and
Thursday, May 22, 2025

Early Bird Ticket

Available until Friday, January 24, 2025
EUR 390 excl. VAT

Regular ticket

EUR 590 excl. VAT

Venue

Hotel Hilton Heidelberg
Kurfürstenanlage 1
D-69115 Heidelberg

Event date

Wednesday, March 5, and
Thursday, March 6, 2025

Tickets

Regular ticket
EUR 590 excl. VAT
Early Bird Ticket

Available until December 24, 2024

EUR 390 excl. VAT
The event is organized by the E3 magazine of the publishing house B4Bmedia.net AG. The presentations will be accompanied by an exhibition of selected SAP partners. The ticket price includes attendance at all presentations of the Steampunk and BTP Summit 2025, a visit to the exhibition area, participation in the evening event and catering during the official program. The lecture program and the list of exhibitors and sponsors (SAP partners) will be published on this website in due course.